Berane

  • Tip: Brownfield
  • Area: 16,6 ha
  • Land ownership: 100% municipal
  • Planning documents: Local site study “Business zone in Berane”
  • Terrain features: Flat
  • Utilities: Connection available
  • Power supply: “Sjekaona” substation 6/0.4 kv which was damaged
  • Telecommunications: No
  • The business zone “Rudeš” was formed by the decision of the Municipality of Berane. The business zone includes the regional business incubator.

Berane

  • Area: 544 km2
  • Population: approximately 27,257
  • Climate: moderate continental in valleys, mountainous in higher altitudes
  • Roads: M-2 highway from the border with Serbia-Rožaje-Berane-Mojkovac leading to Podgorica (Adriatic highway); M-21 highway Barski most-Ribarevina; M-9 highway Kolašin-Mateševo-Andrijevica-Murino-Bjeluha; Regional road R-2 Berane-Andrijevica; Regional road R-7 Most zeleni-Vuča; Regional road R-8 Rožaje-Kula-Stubica; Regional road R-9 Murino-Plav-Gusinje; Regional road R-20 Berane-Stjenica-Kalače.
  • Railway infrastructure: railway station is 36 km away, located in Bijelo Polje (36 km)
  • Airport: there is an airport, but not operational (has a 2 km runway that is 45m wide and a building)
  • Power supply: 3 35/10kV substations
  • Farming land: 29,495 ha (15,803 ha cultivable land, 13,586 ha pastures, 6 ha fish ponds).
  • Forests: 27,856 ha (over 5 million m3 of wood mass)
  • mountains Bjelasica, Smiljevica, Turjak and Komovi, with a large number of peaks above 2,000 m asl, several glacial lakes of rare beauty
  • cultural and historic heritage with a large number of historic monuments

Land that is free for use for a 10 year period, with the obligation of creating new jobs as follows:

  • Areas up to 2500 m2, provided 3-5 workers are employed.
  • Areas up to 5000 m2, provided 6-10 workers are employed.
  • Areas up to 10,000 m2, provided 11-20 workers are employed.

Waiving of fees for the provision of utility infrastructure depending on the type of facility (temporary or permanent)

  • For industrial and community facilities, for utility infrastructure, the fee payable amounts to 50% of the fee for construction of commercial buildings
  • For constructing and erecting temporary structures for conducting business activities, the fee payable amounts to 50% % of the fee for construction of commercial buildings
  • For permanent ancillary facilities (garages, storages and warehouses), the fee payable amounts to 50% of the fee for construction of commercial buildings.
  • The possibility of dividing up of land into smaller parcels – adjusting the areas to suit the needs of prospective investors, in accordance with the investment project demands.
  • Removal of administrative barriers.
  • Public utilities
No. Type Rate
1. Water supply and sanitation 1.29€/m2
2. Solid waste collection and disposal

–        Craft shops

–        Warehouses, wholesales

–        Emptying of large dumpsters

 

0.2-0.27 €/m3

0.17 €/m3

7 m3-66.45 €

 

  • Taxes
  1. Property tax
No. Type of facility Tax rate
1. Business premises 0,35
2. Production facilities (industrial facilities, etc.) 0,1
3. Ancillary facilities 0,23

 

The tax base for the property tax calculation is the market value of the property according to the zone where it is located.

  1. Surtax to personal income tax

The rate of surtax to the personal income tax is defined by the Law on Local Self-Government Funding and amounts to 13%for the Municipality of Berane.

  • Charges
  1. The charge for provision of utility infrastructure to construction land

The table below shows the charge rates depending on the zone (5 zones) for business premises:

Building zone Extra zone I II III IV
Charge rate (€/m2) 25 25 22 20 17.5

 

The average rate of the charge for provision of utility infrastructure is 21.9 €/m2.

  1. The charge for the use of municipal roads
No. TYPE OF CHARGE RATE
1. Annual charge for road land lease

–        Streets in towns and settlements

–        Local roads

–        Uncategorised roads

 

4.9€/m2

3 €/m2

2 €/m2

2. The charge for connecting the access road to a municipal road one-off during the construction stage):

–        Streets in towns and settlements

–        Local roads

–        Uncategorised roads

 

 

800 €

500 €

200 €

3. The charge for placing pipework, water pipes, sewage pipes, power, telephone and telegraph cables along a public road:

 

Urban street:

–        along the road alignment

–        outside the road alignment

–        crossing the road (per crossing)

Local roads:

–        along the road alignment

–        outside the road alignment

–        crossing the road (per crossing)

Uncategorized roads:

–        along the road alignment

–        outside the road alignment

–        crossing the road (per crossing)

 

 

 

 

 

5.5 €/m2

2.9 €/m2

750 €

 

2,9 €/m2

1.5 €/m2

600 €

 

1.5 €/m2

0.5 €/m2

150 €

4. Annual charge for placing and installing electronic, telephone and antennae devices and equipment:

–        one-off (upon instalment)

–        annual

 

 

 

2,500 €

900 €

5. The charge for the use of commercial facilities which have access from a municipal road (annual):

–        hotels

–        restaurants

–        other facilities

100-300 €

30-100 €

30-150 €

6. Charges for placing signboards on and along roadways:

–        depending on the size and type of signboard, annual

 

 

20-150 €

 

 

 

 

  • Municipal Fees
No. TYPE OF MUNICIPAL FEE RATE
1. Fees for asphalt and concrete bases, stone processing bases and sand production 50 €/month

 

2. Fees for wood cutting equipment:

–        bandsaw

–        gutter

–        circular saw

 

 

70 €/month

50 €/ month

10 €/ month

3. Fees for using billboards and panels

(depending on the size and type) (monthly)

Up to 10 €/m2

month

4. The fee for the use of existing and placing new power supply facilities – transmission poles (monthly) 10 €/pc
5. The fee for the use of existing and placing new power supply facilities – distribution poles (monthly) 2€/pc
6. The fee for the use of existing and placing new power supply facilities – substations  35/10 KV (monthly) 150€/pc
7. The fee for the use of existing and placing new power supply facilities – substations (assembly concrete substation, concrete substation, brick-built substation, distribution substation) 80€/pc
8. The fee for the use of existing and placing new power supply facilities – one pillar substations 15€/pc
9. The fee for the use of existing and placing new power supply facilities  – low voltage cabinets (LV cabinets) 25€/pc
10. The fee for the use of telecommunication facilities – mobile phone mast stations 100€/pc
11. The fee for the use of telecommunication facilities – poles and manholes 4€/pc
12. Commercial use of the shore (monthly) 5€/m2

 

Mayor
Dragoslav Šćekić Title Mayor
Tel 051 231 973
E-mail predsjednik@berane.co.me
Mayor’s office
Rade Kljajić Title Deputy Mayor
Tel 051 231 973
E-mail potpredsjednikfin@berane.co.me
Sveto Mitrović Title Deputy Mayor
Tel 051 231 945
E-mail potpredsjednik@berane.co.me
Dr Zoran Marsenić Title Deputy Mayor
Tel 051 231 945
E-mail potpredsjednikdd@berane.co.me
Darko Stojanović Title Manager
Tel +382 51 232177
E-mail manager@berane.co.me
Secretariat for Economy and Finance
Svetomir Aković Title Secretary
Tel 051 231 956
E-mail finansije@berane.co.me